Public cost of training Boeing workers far higher than projections – The Nerve

Posted: October 3, 2021 at 2:58 am

By RICK BRUNDRETT

When S.C. lawmakers in 2009 first approved massive taxpayer-backed funding for aerospace giant Boeing to build an assembly plant in North Charleston, the state estimated it would spend nearly $34 million over 15 years for worker training.

But over the past 10 fiscal years, the state has spent $58.3 million an approximately 70% hike over original projections to train Boeing workers through the S.C. Technical College Systems readySC program, according to information provided this week by the college system to The Nerve.

The average per-worker training cost to the state also jumped significantly, from about $8,950 as initially estimated to approximately $12,100 a 35% increase.

In an email response this week to The Nerve, Technical College System (TCS) spokeswoman Kelly Steinhilper said the readySC program trained 4,831 Boeing workers from fiscal 2012 through last fiscal year, noting that employees on average participated in 30 classes over multiple phases and years. The states original projections covered training for 3,800 workers.

The $58.3 million in training costs over the 10-year period included instructor salary/benefits, equipment and consumable supplies and materials for training, Steinhilper said. Currently, 53 readySC staff are assigned to the Boeing project, she said, with training provided at Boeings plant site or Trident Technical Colleges Aeronautical Training Center in North Charleston an $80 million facility that opened in 2019.

To put the $58.3 million into some context, its more than the entire current budgets of about 60 state agencies or divisions, state budget records show. In comparison, revenues last year for the Chicago-based Boeing totaled about $58.2 billion, company records show nearly $26 billion more than this fiscal years entire state budget.

From fiscal years 2016 through 2020, lawmakers designated a total of more than $43 million for the readySC program out of state general and surplus funds, budget records show.

Effective Jan. 1 of this year, Boeing agreed to begin paying the TCS for worker training, according to documents provided recently to The Nerve by the S.C. Department of Administration under the state Freedom of Information Act.

Those records show that the TCS was authorized to receive about $1.9 million from Boeing in the last half of fiscal 2021, which ended June 30, and another nearly $5 million for this fiscal year.

The State of South Carolina and Boeing have been partners for the last 10 years during which time readySC has provided training for all Boeing production employees under a contractual commitment made when Boeing first began production in the State, according to other-fund authorization requests by the TCS to the Department of Administration. Consequently, readySC now has a highly skilled staff specializing in training of aircraft production employees.

The TCS requests, the latest of which was dated July 12 and approved on July 20 by Brian Gaines, director of the state Executive Budget Office, said Boeing will pay the TCS for all costs incurred to provide this training. Steinhilper said Boeing is paying the personnel costs associated with that (readySC) staff.

Boeing has more than 7,500 workers in South Carolina and about 160,000 worldwide, according to the S.C. Department of Commerces website.

The Nerve launched publication in January 2010 with a week-long investigative series on the Boeing incentives package, conservatively estimating that the cost of all taxpayer-backed freebies totaled at least $500 million. The true cost to taxpayers likely will never be known in part because of state privacy laws protecting companies receiving certain incentives.

Of the state and local incentives offered to Boeing since 2009, state bonds collectively make up much of the taxpayer cost. The general obligation bonds sold to benefit Boeing will cost taxpayers a total of $483.3 million, including $119.3 million in interest, through June 2025, according to information provided this week to The Nerve by the S.C. Treasurers Office.

In a special session in October 2009, lawmakers rushed through an incentives package for Boeing that included approval of an initial $170 million in bonds under a section of the S.C. Constitution that allows legislators to disregard debt ceilings.

Other taxpayer-backed goodies provided to Boeing under a 20-year state incentives agreement provided to The Nerve in 2010 by the Department of Commerce included:

In addition, Charleston County at the time offered Boeing a number of incentives, including, according to county agreements:

Boeing had two existing North Charleston facilities before constructing the 11-football-field-size 787 Dreamliner assembly plant, which started operating in June 2011. In addition, Boeing in 2014 broke ground on a 256,000-square-foot airplane paint hangar, and in 2015 opened a propulsion engineering and assembly facility in North Charleston, according to Commerces website.

Brundrett is the news editor of The Nerve (www.thenerve.org). Contact him at 803-254-4411 or rick@thenerve.org. Follow him on Twitter @RickBrundrett. Follow The Nerve on Facebook and Twitter @thenervesc.

Nervestories are free to reprint and repost with permission by and credit to The Nerve.

See the article here:

Public cost of training Boeing workers far higher than projections - The Nerve