New water records finally released to the Salt Lake Tribune appear to confirm that the National Security Agency's new data storage facility in Bluffdale, Utah, may not be fully operational.
Reporter compelled Bluffdale to provide data on Utah Data Center's water usage.
The data shows that since July 2013, the facility used 6.2 million gallons of water in a month, the highest single month in more than two years of data. For that, the NSA paid $28,596 monthly to the City of Bluffdale, the minimum bill amount.
Under the two entities water contract, that minimum bill jumped to $31,692 as of 2014. However, since July 2013, the monthly water usage fell, rose, and fell again in 2014, reaching a low point of 2.8 million gallons as of February 2014 (the most recent data point).
In October 2013, the Wall Street Journal reported that the Utah Data Center had experienced 10 [electrical] meltdowns in the past 13 months. The paper added that the Utah site continuously draws 65 megawatts of power, which could power a small city of at least 20,000. Bluffdale itself is a small city of 8,000 people, located just south of Salt Lake City. It is also the headquarters of the Apostolic United Brethren, a Mormon fundamentalist group.
The NSA did not respond to Ars repeated requests to find out whether the facility is operational.
The water is believed to be used to cool the massive data center the NSA has been building at the site. In order to accommodate the NSAs water needs, the Tribune reports:
Bluffdale built a $3 million water-delivery system for the center. To ensure it would be able to repay the bond, the city required minimum monthly paymentscalled take or payfrom the NSA. But the contract assumes the NSA will exceed those minimums, at which point Bluffdale begins charging the NSA at a rate that currently amounts to $2.05 per 1,000 gallons.
The version of the contract between the NSA and Bluffdale released by the city redacts the planned amounts of the minimum payments and the Utah Data Centers projected water usage. Its unclear how much more water the NSA could receive with the minimum payment.
When the originalwater records request was denied by the city, the rulingcited legal advice from David Sherman, the associate director for policy and records at the NSA.
Read this article:
New water records show NSA Utah Data Center likely behind schedule
- WikiLeaks' Julian Assange: NSA critics got lucky because agency had no PR strategy [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- National Speakers Association New Jersey Chapter NSA [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- National Security Agency - Wikipedia, the free encyclopedia [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- NSA - Satu Hari Di Bulan Juni (TULUS) (COVER) - Video [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- Hong Kong: Protesters blow whistles for NSA whistle blower - Video [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- An Inside Look at the NSA With Whistleblower William Binney (Part 2 of 2) - Video [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- UK: China will offer fig leaves to US exposed by NSA leaker - Assange - Video [Last Updated On: April 26th, 2014] [Originally Added On: April 26th, 2014]
- NSA ~ (Autodidactism) Whistleblowing - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- Dropping #NSA Knowledge Like a Clumsy Librarian - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- Full Show: Disband The NSA or; Corruption in the Capitol FO SHIZZLE {aTV002} - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- NSA DOCUMENTARY SIX YEARS BEFORE SNOWDEN - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- ShmooCon 2014: The NSA: Capabilities and Countermeasures - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- NSA Knew Of Heartbleed Bug, Refused To Protect Americans - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- Former NSA Head To Become Columnist For Conservative Paper To Discuss Intelligence - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- An Inside Look at the NSA With Whistleblower William Binney (Part 1 of 2) - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- Keynote Address by Shri Shivshankar Menon, NSA at International Seminar on Kautilya - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- NSA Wiretapping: A 4th Amendment Violation?: Blake Norvell at TEDxSMU - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- Hang with Rand: Email Privacy, NSA Spying, and Defending Our Civil Liberties - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- NSA Surveillance and What To Do About It - Bruce Schneier - Video [Last Updated On: April 27th, 2014] [Originally Added On: April 27th, 2014]
- READER SUBMITTED: NSA CT April 2014 Meeting [Last Updated On: April 28th, 2014] [Originally Added On: April 28th, 2014]
- MVI 1847 Obama's NSA Denies FOIA About MH 370! - Video [Last Updated On: April 28th, 2014] [Originally Added On: April 28th, 2014]
- George Galloway's Sputnik: Ewen MacAskill on Guardian / Edward Snowden NSA leaks (26Apr14) - Video [Last Updated On: April 28th, 2014] [Originally Added On: April 28th, 2014]
- CIA & NSA DIRECTED ENERGY WEAPON ATTACK ON WHISTLE BLOWER - Video [Last Updated On: April 28th, 2014] [Originally Added On: April 28th, 2014]
- Book TV - 2014 San Antonio Book Festival: Panel on the NSA, Big Brother, and Democracy - Video [Last Updated On: April 28th, 2014] [Originally Added On: April 28th, 2014]
- NSA Throwdown: John Oliver v. 60 Minutes [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- NSA will sit on security vulnerabilities because of terrorism [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- MVI 1871 NSA Might Be OnTo Me! - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- ZyXEL NSA 325 v2 Hands On - Deutsch / German notebooksbilliger.de - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- German opposition says US should destroy Merkel's NSA file - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- Germany: NSA spying "unacceptable" says SPD - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- NSA Surveillance 2 - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- NSA Surveillance Panel 1 - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- Chalk Talk How Snowden Breached NSA Security - Video [Last Updated On: April 29th, 2014] [Originally Added On: April 29th, 2014]
- NSA reveals some cyber security flaws are left secret [Last Updated On: April 30th, 2014] [Originally Added On: April 30th, 2014]
- NSA data center uses less water than expected [Last Updated On: April 30th, 2014] [Originally Added On: April 30th, 2014]
- April 2014 Breaking News Do you use Google or Yahoo? NSA Intercepts Google And Yahoo Traffic - Video [Last Updated On: April 30th, 2014] [Originally Added On: April 30th, 2014]
- Supreme Court could weigh in on NSA case, justice says [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- New NSA chief: Agency has lost trust [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- NSA on Heartbleed: 'We're not legally allowed to lie to you' [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- What's The NSA Doing Now? Training More Cyberwarriors [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Anonymous NSA - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Cutting off H2O to the NSA - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Brazil: Greenwald slams US media, shares tips to avoid NSA - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- NSA IS TRYINGG 2 KILL ME FAMS - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- What was more popular on Twitter, NSA, NRA or NBA..today? - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- CIS111: NSA Uncovered - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Views from the Street on NSA Activities and Liberty (6/6) - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Views from the Street on NSA Activities and Liberty (4/6) - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Views from the Street on NSA Activities and Liberty (3/6) - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Views from the Street on NSA Activities and Liberty (2/6) - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Views from the Street on NSA Activities and Liberty (1/6) - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Germany: NSA may have accidentally outed secret base - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- ZyXEL NSA 325 v2 Installations-Wizard - Deutsch / German notebooksbilliger.de - Video [Last Updated On: May 1st, 2014] [Originally Added On: May 1st, 2014]
- Tech firms to increase alerts about police requests for data -- report [Last Updated On: May 2nd, 2014] [Originally Added On: May 2nd, 2014]
- German Chancellor Angela Merkel visits US, after the NSA eavesdropping scandal - Video [Last Updated On: May 2nd, 2014] [Originally Added On: May 2nd, 2014]
- NSA spies on more US citizens than Russians Snowden [Last Updated On: May 3rd, 2014] [Originally Added On: May 3rd, 2014]
- THE NEXT NSA?Police under scrutiny for using spying technology [Last Updated On: May 3rd, 2014] [Originally Added On: May 3rd, 2014]
- Ukraine and NSA will test Merkel - Video [Last Updated On: May 3rd, 2014] [Originally Added On: May 3rd, 2014]
- The Latest Attacks On NSA Whistleblower Edward Snowden - Kevin Gosztola Discusses - Video [Last Updated On: May 3rd, 2014] [Originally Added On: May 3rd, 2014]
- Still Report #246 - NSA Classifies MH370 Material - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- Code Talker Induction into NSA Hall of Honor - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- NSA ( National Security Agency ) refusal to release documents on UFO's - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- Obama & NSA Refuse FOIA Request on Malaysia Flight deemed classified - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- Kafkawinstons World`s Channel Terminated NSA is replacing Channel`s with Sockpuppet Channel`s - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- NSA Volunteer Justin Hall at the NSA Comedy Tour February 2014 - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- Barack Obama on NSA Surveillance I'd Be Concerned Too If I Wasn't in Government - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- GBPPR Vision #26: Overview of the NSA's TAWDRYYARD Radar Retro-Reflector - Video [Last Updated On: May 4th, 2014] [Originally Added On: May 4th, 2014]
- NSA proof phone Case - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- 2014 NSA 2014 Million Dollar Publisher's Lab - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- Gen. Michael Hayden - the Former Director of NSA and the CIA - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- REVEALED: Here's The Solution To That Encoded NSA Puzzle Tweet [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- Michael Hayden's Unwitting Case Against Secret Surveillance [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- NSA's Encrypted Tweet: We're Hiring Code Breakers [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- Russ Tice: Life as a NSA Whistleblower - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- What Is Going on at NSA These Days - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- What is the Role of the NSA? AFF Dallas Debates - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- Edward Snowden said CIA , and NSA had 52. 6 Billion for black budget - Video [Last Updated On: May 5th, 2014] [Originally Added On: May 5th, 2014]
- NSA looks to appeal to young cryptographers through coded ads [Last Updated On: May 6th, 2014] [Originally Added On: May 6th, 2014]
- Code Cracked: Mysterious NSA Tweet Is Decrypted in Seconds [Last Updated On: May 6th, 2014] [Originally Added On: May 6th, 2014]
- Breaking: NSA to Rig All Investments for Elite! - Video [Last Updated On: May 6th, 2014] [Originally Added On: May 6th, 2014]