Capstone Reports Strong Second Quarter 2020 Results Growth on Schedule – Business Wire

VANCOUVER, British Columbia--(BUSINESS WIRE)--Capstone Mining Corp. (Capstone or the Company) (TSX:CS) announces its production and financial results for the three (Q2 2020) and six months ended June 30, 2020. Strong copper production totaled 38.5 million pounds of copper despite COVID-19 related production limitations at Cozamin, at consolidated C1 cash costs1 of $1.87 per payable pound produced, 9% lower than Q1 2020. Link HERE for Capstones Q2 2020 managements discussion and analysis (MD&A) and financial statements and HERE for the Q2 webcast presentation.

Q2 results were outstanding and I am proud of everyone for working safely, achieving our planned operational targets and advancing our growth initiatives, despite pandemic-related restrictions, said Darren Pylot, President and CEO of Capstone. Our commitment to growth is evident on multiple fronts, which all comes at an opportune time in line with rising copper and silver prices. Helped by a balance sheet that remains strong, we were able to keep the expansion at Cozamin on track for Q4 2020 completion, and at Pinto Valley the first of two new secondary crushers and ball mill shells were installed last week. Also, we just announced exciting news that we are ramping up cathode operations at Pinto Valley, which will add approximately 300-350 million pounds of low-cost copper cathode production over the next two decades from historic waste dumps and ongoing high-grade waste.

During Q2, we took a number of actions and capitalized on attractive foreign exchange, diesel prices and interest rates to strengthen our balance sheet and improve the Companys liquidity, said Raman Randhawa, SVP and CFO of Capstone. I am happy with Capstones financial position as we are ready to reap the rewards of 20% production growth and 10% lower costs next year, with improving copper and silver prices serving as upside.

HIGHLIGHTS AND SIGNIFICANT ITEMS

Coronavirus (COVID-19) Update

2020 Production and Cost Guidance Reinstated

Capstone is reinstating its original 2020 production and cost guidance as COVID-19 has not to date significantly adversely affected production and costs at our operations. We caution that the global effects and risks of COVID-19 are still evolving. Given the uncertainty of the duration and magnitude of the impact, our production and cash cost estimates are subject to a higher than normal degree of uncertainty. The guidance below does not reflect any potential for additional suspensions or other significant disruption to operations or increased costs due to COVID-19. Refer to the Risk section of the MD&A for further details on COVID-19 related risks.

2020 Guidance

Total

2020 Year-to-date (YTD)

Copper production (million pounds)

140 - 155

74.0

C1 cash costs1

$1.85 - $2.00

$1.96

Capstones capital expenditures are forecasted to be $70 to $80 million and exploration costs to be $7 million for 2020, which positions the Company for expected improvements of 20% production growth and 10% lower costs in 2021.

Balance Sheet Position of Strength

The Companys available liquidity1 improved from $112 million at March 31, 2020 to $136.3 million at June 30, 2020, with cash and short-term investments of $86.2 million and a net debt balance of $163.7 million, and $50.1 million undrawn on the revolving credit facility. Capstones net debt/EBITDA improved during the quarter to 2.54x.

During the quarter amidst COVID-19, Capstone undertook a series of management actions to further strengthen liquidity and manage compliance with banking covenants including the following:

Resilient Growth on Track

Pinto Valley PV3 Optimization Phase 1 and Phase 2 Update

Phase 1 is focused on achieving reliable capacity at 57k tonnes per day (tpd) without major investments in new comminution equipment. In mid-July, Pinto Valley successfully completed over half of Phase 1 work by installing the first of two secondary crushers, three secondary screen decks, as well as the first of two new ball mill shells. The balance of work is on track for completion in Q4 2020 and Q1 2021 with the second secondary crusher and six tertiary screen decks scheduled to arrive later this year and the second ball mill shell scheduled for early 2021.

Phase 2 looks to identify additional opportunities to debottleneck throughput while optimizing flotation plant performance. The target is to secure daily rates of up to 70k tpd along with 85% or higher copper recovery. Some of the scope for Flotation Plant performance will be implemented across the second half of 2020. This includes flotation bank controls, flotation operator training and right-sized rougher concentrate pumps. Additional studies include enhancements to regrind capacity, concentrate dewatering and handling and at the tailings thickener area.

The PV3 Optimization Study is scheduled for release in Q4 2020.

Pinto Valley to Expand Copper Cathode Production

As an extension to the PV3 Optimization strategy, the Company announced on July 27, 2020, that Pinto Valley has successfully demonstrated positive economics from increased dump leach performance using a novel patented catalytic technology developed by Jetti Resources, LLC. In 2019, Jetti started deploying its technology at Pinto Valleys leach operation, and one year later, cathode production per area irrigated has doubled. A plan to increase cathode production is being implemented, with the goal of generating high margin from material that would have been waste at Pinto Valleys underutilized 25 million pound per year electrowinning plant, currently operating at only ~20% of capacity. The plan is to increase cathode production to 300-350 million pounds from residual and high-grade waste over the next two decades, creating 30 new jobs. An updated NI 43-101 Technical Report is expected in 2021.

Cozamin Expansion: 50% Increase to Copper and Silver Production in 2021+

The temporary COVID-19 related ramp down in Q2 2020 did not delay the development of Cozamins one-way ramp, which continues to be on schedule and on budget, expected to be completed in December 2020 and ready for 2021. Production in 2021 and beyond, is expected to increase to a new life of mine annual run rate of approximately 50-55 million pounds of copper and 1.5 million ounces of silver.

During the temporary six-week ramp down, minimal operations safely continued and mining was focused on copper-rich areas, rather than the San Rafael zinc zone, which proved to be a successful trial for our 2021+ production profile. The ore mined during this period is the same type of feed we expect to transition to in 2021. The mill averaged 3,800-3,900 tpd during the days it operated and realized copper recoveries of approximately 96% and silver recoveries of 83%.

Cozamin Expands Resource Estimate by 66%

In June 2020, the Company announced the results of an updated Mineral Resource estimate for Cozamin. The total Measured & Indicated (M&I) Mineral Resource Estimate tonnes increased by 66%, with an 83% increase to contained copper metal to 949 million pounds and a 71% increase to contained silver metal to 39 million ounces of silver. M&I Mineral Resource for Vein 20, the principal zone in the Mala Noche Footwall Zone (MNFWZ), increased by 118% to 13,086 kt at 2.35% Cu and 52 g/t Ag. The Company is currently updating Mineral Reserves and the results of an updated technical report is expected to be announced in Q3 2020.

Cozamin Resumes Exploration Drilling

Exploration drilling at Cozamin was suspended during the six-week ramp down period and has since resumed to execute on an exciting catalogue of exploration targets. Three drills are currently working to infill high grade areas of future reserve target within the new Mineral Resource and trim up open areas immediately on the periphery of the Mineral Resource, to step out up-dip from the high grade Mineral Resource into untested territory and to step out to the southeast across an inferred fault testing a transition from zinc to copper-silver at depth.

The exploration team is currently evaluating a step-out target list for 2021 beyond the MNFWZ system to test our large land package surrounding the current mine. An easy target in 2021 will be Vein 10, located in the hanging wall to the main ore zone, Vein 20. Every hole targeting Vein 20 must first cut Vein 10 in areas of Pb-Zn-Ag-Au mineralization.

Santo Domingo Fulfils Environmental Permit Early Works Requirements

During Q2 2020, Santo Domingo started a limited series of early works, including flora and fauna rescue and site entrance and access roads, in order to preserve the existing Environmental Impact Permit (RCA). These opening works are included in our 2020 budget and are prescribed in the environmental permit and serve to maintain the validity of the permit and are scheduled for completion in Q4 2020.

Activity and interest in participating in the project via the strategic sales process have increased in Q2 2020. In addition, we have received substantial interest in sharing or mutually developing off-site infrastructure that is delineated in the NI 43-101 Technical Report and valued at approximately $500 million. Ongoing discussions and negotiations are progressing with the objective of substantially reducing the project capital costs and operational risk, while maintaining the Life of Mine profitability.

OPERATIONAL AND FINANCIAL OVERVIEW

Operational Overview

Refer to Capstones Q2 2020 MD&A and Financial Statements for detailed operating results.

Q2 2020

Q2 2019

2020 YTD

2019 YTD

Copper production (million pounds)

Pinto Valley

30.2

29.0

57.0

61.7

Cozamin

8.3

8.7

17.0

17.4

Total copper production (million pounds)

38.5

37.7

74.0

79.1

Copper sales

Total copper sales (from continuing operations)2 (million pounds)

37.8

45.5

68.3

80.9

Realized copper price ($/lb.)

2.72

2.56

2.53

2.75

C1 cash costs1 ($/lb.) produced

Pinto Valley

2.12

2.00

2.25

1.89

Cozamin

0.98

1.06

0.97

0.88

Consolidated C1 cash costs1 ($/lb.) produced

1.87

1.78

1.96

1.67

2 Sales from continuing operations has been utilized due to the Minto mine being classified as a discontinued operation in the comparative period until the point of its sale on June 3, 2019.

Consolidated

When compared to the same period last year, Q2 2020 production of 38.5 million pounds was 2% higher primarily due to increased production at Pinto Valley as a result of the increased focus on maximizing mill throughput in 2020 (53,864 tpd vs. 49,121 tpd in H1 2019). This increase was slightly offset by a decrease in production at Cozamin due to a temporary reduction of operations to comply with a Mexican government decree in response to COVID-19.

2020 YTD total production is lower than the same period last year primarily due to a lower planned head grade (0.30% vs. 0.34%) at Pinto Valley.

In Q2 2019 and 2019 YTD, sales were higher than production due to a drawdown of inventory at Pinto Valley. Inventory levels were higher in early 2019 to benefit from improved expected sales terms.

Pinto Valley Mine

C1 cash costs1 of $2.12 per pound in Q2 2020 were higher than Q2 2019, primarily due to lower capitalized stripping ($0.7 million vs. $6.7 million in 2019), partially offset by higher copper production.

Property cost per tonne milled1 of $10.86 in Q2 2020 was $0.31/tonne lower (-3%) versus the average cost per tonne milled in 2019 and $0.77/tonne (-6%) lower than in 2018.

Cozamin Mine

C1 cash costs1 were lower in Q2 2020 vs. Q2 2019. Costs were lower from reduced operating development meters and utility cost savings realized during the ramp down of operations in Q2 2020. The mine safely ramped up to full production levels by June 1st after the Mexican government declared mining as an essential service.

Financial Overview

Follow this link:

Capstone Reports Strong Second Quarter 2020 Results Growth on Schedule - Business Wire

Related Posts

Comments are closed.