NASA OIG on Webb and Recovery Act Funds

NASA OIG: NASA's Use of Recovery Act Funding for the James Webb Space Telescope Project

"Following multiple schedule delays and substantial cost growth, in 2009 the JWST Project received $75 million in Recovery Act funding intended to sustain the Project's workforce at a consistent level and maintain the baseline schedule for key development activities. We found that in using these funds, the JWST Project adequately addressed the requirements of the Recovery Act and related OMB guidance and delivered measureable outcomes consistent with Agency program and project plans and the goals of the Act. Specifically, we found that the $75 million in Recovery Act funds enabled 454 jobs to be retained on the JWST Project in the fourth quarter of FY 2009 and 149 jobs in the first quarter of FY 2010."